排山楼黄金矿业公司选矿厂原处理能力1200 t/d,后陆续扩建至3000 t/d,而碎矿配套除尘系统一直没有更新,除尘效果不好,工作环境较差,严重影响职工的身体健康。2012年,该公司采用高效滤筒除尘技术对碎矿除尘系统进行了整体改造,改造后粉尘指标远低于国家标准,取得了较好的经济效益、环境效益和社会效益。

The production capacity of the ore dressing plant in Paishanlou Gold Mine was 1 200 t/d which has been now expanded to 3 000 t/d,but the crushing ancillary dedusting system has not been updated,the bad dust re-moval effect and poor working environment seriously affecting the health of workers.In 2012 the company adopted filter dust removal technology for the overall transformation of the crushing dust removal system,dust after the transformation has been far below national standards,achievingeconomic,environmental and social benefits.

参考文献

[1] 范乃和.选厂破碎除尘方法探讨[J].金属矿山,2003(11):52-54.
[2] 齐振龙,张树林,郜旭.金渠金矿破碎车间除尘设备的改造及应用[J].黄金,2012(01):35-37.
[3] 沈发根.某选厂破碎车间除尘工艺设计及设备选择[J].现代矿业,2010(10):134-135.
[4] 贡锁国.矿石破碎防尘及除尘技术[J].矿业快报,2002(08):18-20.
上一张 下一张
上一张 下一张
计量
  • 下载量()
  • 访问量()
文章评分
  • 您的评分:
  • 1
    0%
  • 2
    0%
  • 3
    0%
  • 4
    0%
  • 5
    0%