针对田兴铁矿1#主井井壁突水情况及井壁裂隙破碎带的结构特点,介绍了在出水点埋设3根导水管将井壁涌水引入工作面水窝,再浇筑混凝土井壁形成支撑结构防止围岩失稳、裂隙扩展,最后待浇筑混凝土养护后对其壁后注浆封水的突水治理方案。其中,壁后注浆采用上行式注浆,由下而上逐步推进注浆封水,注浆孔分3层上下菱形交错布置。经过井壁突水综合治理方案的实施,田兴铁矿1#主井井壁裂隙破碎带涌水从最初的64 m3/h降到近20 m3/h,对井壁涌水起到了封堵作用,有效保障了后续井筒下掘施工的安全。

According to the situation of 1#main shaft water inrush and the characteristic of wall cracks ,three aq-ueducts buried at the water point were used to put water into nest ,then concrete wall was formed to prevent instability of surrounding rock and crack propagation ,and finally back grouting where grouting hole was divided into three layers on the diamond staggered arrangement and the upward grouting was used for water shutoff was adopted when wall ma -intenance has reached the standard .Through effective execution of comprehensive control technology ,the shaft water has been reduced from 64 cubic meters per hour to as low as 20 cubic meters per hour ,effectively shutting off water in-rush and guaranteeing the safety operation of following excavation construction .

参考文献

[1] 李玉杰,王连国,陆银龙,孙琎
[2] 王长春,周晓军.地下水对隧道衬砌结构力学行为影响的研究[J].四川建筑,2004(06):79-80.
[3] 崔秀平.竖井施工及井壁支护[J].科技传播,2012(14):145-146.
[4] 匡永志,蒙光林,马春德,万串串.壁后注浆固结技术在破碎岩体中施工主水仓的应用[J].矿业研究与开发,2011(02):32-34.
[5] 刘风坤,舒非凡.立井井筒壁后注浆施工[J].建井技术,2008(02):21-22,5.
[6] 翟会超,闫满志.田兴铁矿3#主井注浆施工技术[J].现代矿业,2012(12):117-118.
上一张 下一张
上一张 下一张
计量
  • 下载量()
  • 访问量()
文章评分
  • 您的评分:
  • 1
    0%
  • 2
    0%
  • 3
    0%
  • 4
    0%
  • 5
    0%